Home addition
In production
| Value | $56,200 |
| Where | Wendell |
| Start date | 2026-06-02 |
| Target complete date | 2026-09-11 |
| Progress | 58% |
Budget vs actual by trade
budgetactual
| Category | budget | actual |
|---|---|---|
| Cabinets | 4,431 | 3,176 |
| Framing | 4,139 | 3,332 |
| Drywall | 3,918 | 2,572 |
| Paint | 3,250 | 2,460 |
| Concrete | 3,197 | 2,912 |
| Flooring | 2,954 | 2,132 |
| Plumbing | 2,790 | 2,136 |
| Electrical | 2,516 | 1,814 |
| Demo | 2,144 | 1,607 |
| Cleanup | 2,041 | 1,486 |
Materials ordered
| Category | Value |
|---|---|
| Millwork | 16K |
| Plumbing | 2,002 |
| Tools & Safety | 1,788 |
| Drywall | 1,558 |
Purchase orders
| PO-2606-015 | Tri-County Hardware | received | $21,227 |
Billed
| Invoiced | $32,596 |
| Paid | $32,596 |
| Outstanding | $0 |
Activity
| 2026-07-20 | Inspection | Final inspection scheduled | Tanya Boone |
| 2026-07-18 | Crew on site | Crew pulled to Four Oaks for the morning | Tanya Boone |
| 2026-07-14 | Crew on site | Framing crew, 4 on site | Tanya Boone |
| 2026-07-14 | Material delivery | Delivery received against PO-2606-015 | Wes Tanner |
| 2026-06-30 | Crew on site | Framing crew, 4 on site | Tanya Boone |
| 2026-06-27 | Client meeting | Adjuster on site | Hector Alvarez |
| 2026-06-18 | Delay | Client hold pending selection | Bo Wingate |
| 2026-06-12 | Material delivery | Delivery received against PO-2606-015 | Tanya Boone |