Fire rebuild, partial interior

In production

Value$23,100
WherePine Level
Start date2026-06-24
Target complete date2026-09-04
Progress51%

Budget vs actual by trade

Drywall0.81xRoofing0.75xFlooring0.69xPaint0.70xDemo0.60xFraming0.67xCabinets0.75xPlumbing0.71xElectrical0.77xHVAC0.77x
budgetactual
Categorybudgetactual
Drywall1,6511,338
Roofing1,4981,116
Flooring1,369944.69
Paint1,355953.78
Demo1,232737.65
Framing1,200805.26
Cabinets932702.74
Plumbing900641.79
Electrical891682.83
HVAC736568.12

Materials ordered

Plumbing1,520Electrical1,045Tools & Safety544.12
CategoryValue
Plumbing1,520
Electrical1,045
Tools & Safety544.12

Purchase orders

PO-2607-009Eastway Electrical Supplyreceived$3,109

Billed

Invoiced$11,781
Paid$0
Outstanding$11,781

Activity

2026-07-29Material deliveryDelivery refused, wrong item on the truckTanya Boone
2026-07-28Client meetingWalkthrough with clientTanya Boone
2026-07-26Material deliveryDelivery refused, wrong item on the truckTanya Boone
2026-07-19Client meetingAdjuster on siteTanya Boone
2026-07-18DelayRain day, no productionOmar Fadel
2026-07-18InspectionInspection failed, re-scheduledTanya Boone
2026-07-13DelayClient hold pending selectionTanya Boone
2026-07-11Material deliveryDelivery received against PO-2607-009Levi Stroud
2026-07-10DelayClient hold pending selectionTanya Boone
2026-07-07Material deliveryDelivery received against PO-2607-009Trey Boykin
2026-07-06Crew on siteCrew pulled to Smithfield for the morningTanya Boone
2026-07-01Crew on siteTwo-man crew, punch itemsDanny Kwan
2026-06-26InspectionRough-in inspection passedLevi Stroud