In production

Value$172,900
WhereArcher Lodge
Start date2026-06-23
Target complete date2026-11-14
Progress32%

Budget vs actual by trade

Electrical0.16xHVAC0.29xDrywall0.30xFraming0.37xConcrete0.37xPlumbing0.30xPaint0.29xFlooring0.28xDemo0.29xRoofing0.30x
budgetactual
Categorybudgetactual
Electrical16K2,566
HVAC15K4,455
Drywall13K3,821
Framing12K4,549
Concrete12K4,561
Plumbing8,2502,509
Paint7,8942,276
Flooring6,6961,891
Demo6,4071,884
Roofing6,1001,821

Materials ordered

Paint & Sundries19KConcrete & Masonry18KLumber2,617Roofing487.65Electrical135.78
CategoryValue
Paint & Sundries19K
Concrete & Masonry18K
Lumber2,617
Roofing487.65
Electrical135.78

Purchase orders

PO-2607-008Coastal Lumber & Millworkreceived$40,616

Billed

Invoiced$59,816
Paid$26,938
Outstanding$32,879

Activity

2026-07-30Punch listFinal clean scheduledHector Alvarez
2026-07-28Crew on siteFraming crew, 2 on siteCurt Hollis
2026-07-22DelayRain day, no productionCurt Hollis
2026-07-20Crew on siteFraming crew, 4 on siteJamal Prince
2026-07-19Client meetingWalkthrough with clientCurt Hollis
2026-07-19Material deliveryDelivery refused, wrong item on the truckSam Odum
2026-07-17Crew on siteFraming crew, 2 on siteCurt Hollis
2026-07-15Material deliveryPartial delivery, backordered items to followCurt Hollis
2026-07-12DelayWaiting on material, flooring heldCurt Hollis
2026-07-10Crew on siteCrew pulled to Wilson for the morningCurt Hollis
2026-07-05Client meetingAdjuster on siteCurt Hollis
2026-07-04Crew on siteTwo-man crew, punch itemsCurt Hollis
2026-07-02Client meetingAdjuster on siteCurt Hollis
2026-06-30Material deliveryDelivery refused, wrong item on the truckIke Ferrell