Fire rebuild, partial interior
In production
| Value | $172,400 |
| Where | Smithfield |
| Start date | 2026-07-05 |
| Target complete date | 2026-12-09 |
| Progress | 14% |
Budget vs actual by trade
budgetactual
| Category | budget | actual |
|---|---|---|
| Drywall | 14K | 2,098 |
| Flooring | 11K | 1,619 |
| Roofing | 11K | 1,590 |
| Demo | 9,108 | 1,449 |
| Paint | 8,970 | 1,420 |
| Framing | 8,477 | 1,584 |
| Plumbing | 7,524 | 1,185 |
| Cabinets | 6,833 | 728.35 |
| Cleanup | 6,254 | 941.71 |
| Electrical | 5,865 | 849.62 |
Materials ordered
| Category | Value |
|---|---|
| Plumbing | 1,837 |
Purchase orders
| PO-2607-015 | Piedmont Building Supply | received | $1,837 |
Billed
| Invoiced | $28,606 |
| Paid | $0 |
| Outstanding | $28,606 |
Activity
| 2026-07-26 | Crew on site | Crew pulled to Wilson's Mills for the morning | Levi Stroud |
| 2026-07-21 | Client meeting | Adjuster on site | Marisol Ibarra |
| 2026-07-20 | Crew on site | Framing crew, 3 on site | Marisol Ibarra |
| 2026-07-19 | Punch list | Final clean scheduled | Marisol Ibarra |
| 2026-07-17 | Client meeting | Adjuster on site | Trey Boykin |
| 2026-07-15 | Material delivery | Delivery refused, wrong item on the truck | Marisol Ibarra |
| 2026-07-11 | Crew on site | Two-man crew, punch items | Marisol Ibarra |
| 2026-07-07 | Delay | Waiting on plumbing sub | Marisol Ibarra |
| 2026-07-06 | Material delivery | Delivery refused, wrong item on the truck | Trey Boykin |
| 2026-07-05 | Inspection | Inspection failed, re-scheduled | Marisol Ibarra |
| 2026-07-05 | Client meeting | Adjuster on site | Marisol Ibarra |