Storm / tree impact
In production
| Value | $49,500 |
| Where | Pine Level |
| Start date | 2026-07-06 |
| Target complete date | 2026-09-12 |
| Progress | 37% |
Budget vs actual by trade
budgetactual
| Category | budget | actual |
|---|---|---|
| Drywall | 3,728 | 1,471 |
| Roofing | 3,159 | 1,314 |
| Paint | 3,091 | 591.46 |
| Flooring | 2,910 | 1,156 |
| Framing | 2,503 | 1,094 |
| Demo | 2,433 | 793.11 |
| Plumbing | 2,166 | 757.17 |
| Cabinets | 1,945 | 375.24 |
| Cleanup | 1,919 | 749.04 |
| HVAC | 1,748 | 656.85 |
Materials ordered
| Category | Value |
|---|---|
| Roofing | 9,339 |
| Plumbing | 9,166 |
| Millwork | 5,770 |
| Flooring | 2,269 |
| Electrical | 88.69 |
Purchase orders
| PO-2607-016 | Tri-County Hardware | received | $26,633 |
Billed
| Invoiced | $18,315 |
| Paid | $0 |
| Outstanding | $18,315 |
Activity
| 2026-07-29 | Inspection | Final inspection scheduled | Curt Hollis |
| 2026-07-25 | Client meeting | Adjuster on site | Curt Hollis |
| 2026-07-24 | Client meeting | Walkthrough with client | Curt Hollis |
| 2026-07-22 | Material delivery | Partial delivery, backordered items to follow | Curt Hollis |
| 2026-07-19 | Delay | Client hold pending selection | Curt Hollis |
| 2026-07-19 | Delay | Waiting on paint sub | Omar Fadel |
| 2026-07-16 | Material delivery | Delivery received against PO-2607-016 | Sam Odum |
| 2026-07-12 | Inspection | Framing inspection passed | Curt Hollis |
| 2026-07-11 | Crew on site | Two-man crew, punch items | Levi Stroud |
| 2026-07-10 | Crew on site | Framing crew, 4 on site | Curt Hollis |
| 2026-07-06 | Delay | Waiting on material, cabinets held | Curt Hollis |