Master suite addition
In production
| Value | $88,800 |
| Where | Princeton |
| Start date | 2026-07-02 |
| Target complete date | 2026-11-11 |
| Progress | 21% |
Budget vs actual by trade
budgetactual
| Category | budget | actual |
|---|---|---|
| Cabinets | 8,086 | 2,665 |
| Framing | 7,367 | 1,393 |
| Flooring | 5,217 | 1,637 |
| Paint | 5,110 | 1,268 |
| Drywall | 4,770 | 1,520 |
| Plumbing | 4,432 | 1,446 |
| Concrete | 4,062 | 1,462 |
| Electrical | 3,468 | 866.07 |
| Demo | 3,085 | 918.76 |
| HVAC | 2,776 | 826.62 |
Materials ordered
| Category | Value |
|---|---|
| Electrical | 10K |
| Plumbing | 3,949 |
| Drywall | 1,515 |
Purchase orders
| PO-2607-011 | Coastal Lumber & Millwork | on order | $15,948 |
Billed
| Invoiced | $18,648 |
| Paid | $0 |
| Outstanding | $18,648 |
Activity
| 2026-07-29 | Punch list | Punch list issued | Curt Hollis |
| 2026-07-25 | Delay | Waiting on material, masonry held | Curt Hollis |
| 2026-07-25 | Client meeting | Selections meeting | Curt Hollis |
| 2026-07-24 | Material delivery | Partial delivery, backordered items to follow | Curt Hollis |
| 2026-07-22 | Material delivery | Delivery received against PO-2607-011 | Levi Stroud |
| 2026-07-18 | Delay | Waiting on material, cleanup held | Curt Hollis |
| 2026-07-15 | Crew on site | Framing crew, 5 on site | Curt Hollis |
| 2026-07-13 | Punch list | Punch list issued | Levi Stroud |
| 2026-07-10 | Crew on site | Two-man crew, punch items | Curt Hollis |
| 2026-07-08 | Punch list | Punch list issued | Curt Hollis |
| 2026-07-05 | Crew on site | Crew pulled to Benson for the morning | Curt Hollis |
| 2026-07-03 | Delay | Waiting on material, electrical held | Curt Hollis |