Storm / tree impact
In production
| Value | $123,400 |
| Where | Pine Level |
| Start date | 2026-07-19 |
| Target complete date | 2026-12-01 |
| Progress | 7% |
Budget vs actual by trade
budgetactual
| Category | budget | actual |
|---|---|---|
| Roofing | 8,531 | 190.65 |
| Drywall | 8,525 | 642.61 |
| Flooring | 7,643 | 604.92 |
| Paint | 6,795 | 534.70 |
| Cleanup | 6,784 | 527.73 |
| Demo | 6,207 | 454.20 |
| Cabinets | 6,126 | 481.93 |
| Framing | 5,417 | 436.16 |
| Electrical | 5,138 | 380.41 |
| Plumbing | 4,401 | 95.12 |
Materials ordered
| Category | Value |
|---|---|
| Paint & Sundries | 10K |
| Drywall | 3,345 |
| Tools & Safety | 2,263 |
| Roofing | 835.92 |
| Plumbing | 84.84 |
Purchase orders
| PO-2607-024 | Granite State Surfaces | on order | $16,626 |
Billed
| Invoiced | $8,638 |
| Paid | $0 |
| Outstanding | $8,638 |
Activity
| 2026-07-30 | Crew on site | Two-man crew, punch items | Sam Odum |
| 2026-07-30 | Delay | Waiting on cleanup sub | Tanya Boone |
| 2026-07-29 | Crew on site | Framing crew, 2 on site | Danny Kwan |
| 2026-07-29 | Delay | Waiting on cleanup sub | Tanya Boone |
| 2026-07-27 | Crew on site | Two-man crew, punch items | Trey Boykin |
| 2026-07-27 | Delay | Rain day, no production | Tanya Boone |
| 2026-07-23 | Client meeting | Selections meeting | Tanya Boone |
| 2026-07-22 | Crew on site | Crew pulled to Clayton for the morning | Bo Wingate |
| 2026-07-22 | Material delivery | Delivery received against PO-2607-024 | Tanya Boone |
| 2026-07-21 | Client meeting | Selections meeting | Omar Fadel |
| 2026-07-21 | Delay | Rain day, no production | Sam Odum |
| 2026-07-21 | Inspection | Framing inspection passed | Tanya Boone |