Deck, patio + retaining wall

J-260710 · Wilson's Mills
Data updated 12:46Checked 12:46Sign in Refresh
Sample data. Every figure, product and customer name is invented to show the shape of the tool. Real numbers appear once your own data is loaded.

← All jobs

Deck, patio + retaining wall

In production · overdue

Value$19,300
WhereWilson's Mills
Start date2026-07-18
Target complete date2026-08-20
Progress46%

Budget vs actual by trade

Concrete0.55xMasonry0.39xFraming0.43xElectrical0.24xDemo0.42xPaint0.41xCleanup0.40x
budgetactual
Categorybudgetactual
Concrete4,0632,254
Masonry3,1121,206
Framing855370.66
Electrical844205.88
Demo763317.03
Paint619256.58
Cleanup605240.55

Materials ordered

Paint & Sundries6,862Tools & Safety1,091
CategoryValue
Paint & Sundries6,862
Tools & Safety1,091

Purchase orders

PO-2607-023Carolina Tile Depotreceived$7,953

Billed

Invoiced$8,878
Paid$0
Outstanding$8,878

Activity

2026-07-30Crew on siteFraming crew, 6 on siteRay Delgado
2026-07-27InspectionInspection failed, re-scheduledRay Delgado
2026-07-27Crew on siteCrew pulled to Archer Lodge for the morningRay Delgado
2026-07-26Material deliveryDelivery received against PO-2607-023Trey Boykin
2026-07-25Crew on siteCrew pulled to Micro for the morningWes Tanner
2026-07-25Crew on siteTwo-man crew, punch itemsRay Delgado
2026-07-25Material deliveryPartial delivery, backordered items to followLevi Stroud
2026-07-23Client meetingSelections meetingRay Delgado
2026-07-23Material deliveryPartial delivery, backordered items to followOmar Fadel
2026-07-23Crew on siteCrew pulled to Wilson's Mills for the morningLevi Stroud
2026-07-21DelayWaiting on masonry subRay Delgado
2026-07-20Crew on siteFraming crew, 6 on siteHector Alvarez
2026-07-20DelayRain day, no productionRay Delgado
2026-07-19Crew on siteFraming crew, 5 on siteRay Delgado