Retail buildout

In production

Value$142,000
WherePine level
Start date2026-07-04
Target complete date2026-12-12
Progress27%

Budget vs actual by trade

Electrical0.46xHVAC0.49xFraming0.29xConcrete0.43xDrywall0.46xPlumbing0.50xPaint0.49xDemo0.49xRoofing0.49xFlooring0.54x
budgetactual
Categorybudgetactual
Electrical14K6,403
HVAC11K5,550
Framing11K3,164
Concrete10K4,546
Drywall9,5294,426
Plumbing8,3524,139
Paint7,5483,702
Demo6,6453,240
Roofing4,9882,446
Flooring4,5762,468

Materials ordered

Concrete & Masonry12KPaint & Sundries12KElectrical8,300Plumbing4,612Flooring3,818Lumber587.10
CategoryValue
Concrete & Masonry12K
Paint & Sundries12K
Electrical8,300
Plumbing4,612
Flooring3,818
Lumber587.10

Purchase orders

PO-2607-014Eastway Electrical Supplyreceived$40,323
PO-2607-013Eastway Electrical Supplyreceived$826

Billed

Invoiced$38,340
Paid$0
Outstanding$38,340

Activity

2026-07-30Material deliveryDelivery refused, wrong item on the truckTanya Boone
2026-07-29Client meetingAdjuster on siteTanya Boone
2026-07-22Crew on siteTwo-man crew, punch itemsIke Ferrell
2026-07-21Client meetingSelections meetingTanya Boone
2026-07-18InspectionFinal inspection scheduledTanya Boone
2026-07-15DelayClient hold pending selectionTanya Boone
2026-07-15Crew on siteFraming crew, 2 on siteTanya Boone