Fire rebuild, partial interior

J-260712 ยท Zebulon
Data updated 12:46Checked 12:46Sign in Refresh
Sample data. Every figure, product and customer name is invented to show the shape of the tool. Real numbers appear once your own data is loaded.

← All jobs

Fire rebuild, partial interior

In production

Value$103,500
WhereZebulon
Start date2026-07-15
Target complete date2026-11-16
Progress11%

Budget vs actual by trade

Roofing0.08xDrywall0.09xPaint0.09xFlooring0.10xDemo0.09xFraming0.10xPlumbing0.09xCabinets0.05xElectrical0.08xHVAC0.09x
budgetactual
Categorybudgetactual
Roofing7,244613.20
Drywall6,666608.56
Paint6,092525.04
Flooring6,068592.95
Demo6,003549.73
Framing4,808489.40
Plumbing3,962343.94
Cabinets3,843190.25
Electrical3,817310.12
HVAC3,699318.89

Materials ordered

Electrical398.10Plumbing291.84
CategoryValue
Electrical398.10
Plumbing291.84

Purchase orders

PO-2607-021Coastal Lumber & Millworkreceived$690

Billed

Invoiced$11,385
Paid$0
Outstanding$11,385

Activity

2026-07-29InspectionInspection failed, re-scheduledJamal Prince
2026-07-27Material deliveryPartial delivery, backordered items to followRay Delgado
2026-07-24DelayWaiting on hvac subRay Delgado
2026-07-22Crew on siteCrew pulled to Clayton for the morningRay Delgado