Fire rebuild, partial interior
In production
| Value | $103,500 |
| Where | Zebulon |
| Start date | 2026-07-15 |
| Target complete date | 2026-11-16 |
| Progress | 11% |
Budget vs actual by trade
budgetactual
| Category | budget | actual |
|---|---|---|
| Roofing | 7,244 | 613.20 |
| Drywall | 6,666 | 608.56 |
| Paint | 6,092 | 525.04 |
| Flooring | 6,068 | 592.95 |
| Demo | 6,003 | 549.73 |
| Framing | 4,808 | 489.40 |
| Plumbing | 3,962 | 343.94 |
| Cabinets | 3,843 | 190.25 |
| Electrical | 3,817 | 310.12 |
| HVAC | 3,699 | 318.89 |
Materials ordered
| Category | Value |
|---|---|
| Electrical | 398.10 |
| Plumbing | 291.84 |
Purchase orders
| PO-2607-021 | Coastal Lumber & Millwork | received | $690 |
Billed
| Invoiced | $11,385 |
| Paid | $0 |
| Outstanding | $11,385 |
Activity
| 2026-07-29 | Inspection | Inspection failed, re-scheduled | Jamal Prince |
| 2026-07-27 | Material delivery | Partial delivery, backordered items to follow | Ray Delgado |
| 2026-07-24 | Delay | Waiting on hvac sub | Ray Delgado |
| 2026-07-22 | Crew on site | Crew pulled to Clayton for the morning | Ray Delgado |