Tenant upfit, 2nd floor
Signed, mobilising
| Value | $237,600 |
| Where | Wendell |
| Start date | 2026-07-10 |
| Target complete date | 2027-01-06 |
| Progress | 6% |
Budget vs actual by trade
budgetactual
| Category | budget | actual |
|---|---|---|
| Electrical | 23K | 486.28 |
| HVAC | 22K | 413.96 |
| Framing | 20K | 476.68 |
| Drywall | 18K | 232.13 |
| Concrete | 15K | 370.59 |
| Plumbing | 14K | 256.68 |
| Paint | 11K | 84.91 |
| Demo | 11K | 189.38 |
| Roofing | 8,545 | 63.66 |
| Flooring | 5,623 | 47.84 |
Materials ordered
| Category | Value |
|---|---|
| Plumbing | 905.40 |
| Lumber | 418 |
| Concrete & Masonry | 192 |
Purchase orders
| PO-2607-017 | Coastal Lumber & Millwork | received | $1,515 |
Billed
| Invoiced | $14,256 |
| Paid | $0 |
| Outstanding | $14,256 |
Activity
| 2026-07-30 | Crew on site | Crew pulled to Pine Level for the morning | Tanya Boone |
| 2026-07-29 | Material delivery | Partial delivery, backordered items to follow | Ike Ferrell |
| 2026-07-25 | Inspection | Framing inspection passed | Tanya Boone |
| 2026-07-25 | Client meeting | Adjuster on site | Tanya Boone |
| 2026-07-22 | Crew on site | Two-man crew, punch items | Tanya Boone |
| 2026-07-18 | Punch list | Punch list issued | Levi Stroud |
| 2026-07-18 | Crew on site | Crew pulled to Micro for the morning | Tanya Boone |
| 2026-07-16 | Punch list | Punch items closed out | Tanya Boone |