Deck, patio + retaining wall
Signed, mobilising
| Value | $8,500 |
| Where | Archer Lodge |
| Start date | 2026-07-30 |
| Target complete date | 2026-08-28 |
| Progress | 2% |
Budget vs actual by trade
budgetactual
| Category | budget | actual |
|---|---|---|
| Concrete | 1,604 | 396.37 |
| Masonry | 1,385 | 287 |
Activity
| 2026-08-03 | Material delivery | Delivery received against the open PO | Ray Delgado |
| 2026-08-03 | Crew on site | Framing crew, 3 on site | Ray Delgado |
| 2026-08-02 | Crew on site | Framing crew, 4 on site | Ray Delgado |
| 2026-08-02 | Inspection | Rough-in inspection passed | Ray Delgado |
| 2026-08-01 | Client meeting | Selections meeting | Ike Ferrell |
| 2026-08-01 | Delay | Waiting on masonry sub | Ray Delgado |
| 2026-07-31 | Punch list | Final clean scheduled | Levi Stroud |
| 2026-07-31 | Material delivery | Delivery received against the open PO | Ray Delgado |
| 2026-07-30 | Crew on site | Crew pulled to Pine Level for the morning | Trey Boykin |
| 2026-07-30 | Material delivery | Partial delivery, backordered items to follow | Wes Tanner |
| 2026-07-30 | Material delivery | Partial delivery, backordered items to follow | Sam Odum |